In this section you will learn how to revise existing pipelines.
Topics
Copy Piping copies an existing pipeline or a group of components to a specified location in the model. Select Placement from the Piping pull-down menu. | |
Rotate Piping rotates existing piping in the active model. You can rotate a pipeline or the elements defined by the active group by a specified angle of rotation. Select Revise Component from the Piping pull-down menu. | |
Copy and Rotate Piping places a rotated copy of an existing pipeline or group of components. Select Placement from the Piping pull-down menu. | |
Mirror Piping mirrors existing piping to a specified location in the active model. Select Revise Group from the Piping pull-down menu. | |
Copy and Mirror Piping creates a mirrored copy of an existing pipeline or group of components. Select Placement from the Piping pull-down menu. | |
Move Piping moves an entire pipeline or move the elements defined by the active group to a specified location. Select Revise Group from the Piping pull-down menu. | |
Move Pipe Run moves a specified pipe run to a new location while maintaining the connectivity to the connecting pipe runs in the piping segment. Select Revise Group from the Piping pull-down menu. | |
Move Pipeline End moves a pipeline's end point to a new location. Select Placement from the Piping pull-down menu. | |
Replace Piping provides you with the ability to replace all the piping commodities of a specific name within a working group with a different commodity name and/or commodity option. Select Revise Group from the Piping pull-down menu. | |
Reconstruct Piping reconstructs a specified part of the model to update the graphical representation and the alphanumeric data associated with that piping, based on changes in the Piping Design RDB, the P&ID MDB, or the piping segment data in the model. Select Revise Group from the Piping pull-down menu. | |
Lab Exercises |
Copy Piping Exercise
Copy an existing pipeline to another location.
Note:
See Copy Piping for reference information.
1. Identify the pipeline at CP1 of the flange.
The system highlights the pipeline.
2. Identify the equipment/nozzle.
The system places the piping segment at the new location.
3. Accept the form with Confirm.
The system updates the database and the graphics.
Rotate Piping Exercise
Rotate the existing pipeline.
Note:
See Rotate Piping for reference information.
1. Identify the pipeline.
The system highlights the pipeline.
2. Select Plan View.
3. Key in 180.
The system places the piping segments at the new orientation.
4. Accept the form with Confirm.
The system updates the database and the graphics.
Copy and Rotate Piping Exercise
Copy and rotate an existing pipeline to a new location.
Note:
See Copy and Rotate Piping for reference information.
1. Identify the pipeline at CP1 of the flange.
The system highlights the pipeline.
2. Identify the equipment nozzle.
3. Select Plan View.
4. Key in 180.
The system reorients the piping segment at its new location.
5. Accept the form with Confirm.
The system updates the database and the graphics.
Mirror Piping Exercise
Mirror an existing pipeline to a new location.
Note:
See Mirror Piping for reference information.
1. Identify the pipeline.
The system highlights the pipeline.
2. Select Move East and key in 5'6" (1676 mm).
The system reorients the piping segments.
3. Accept the form with Confirm.
The system updates the database and the graphics.
Copy and Mirror Piping Exercise
Copy and mirror an existing pipeline to a new location.
Note:
See Copy and Mirror Piping for reference information.
1. Identify the pipeline at CP1 of the flange.
The system highlights the pipeline.
2. Identify the equipment nozzle.
The system reorients the piping segment at its new location.
3. Accept the form with Confirm.
The system updates the database and the graphics.
Move Piping Exercise
Move an existing pipeline to a new location.
Note:
See Move Piping for reference information.
1. Identify the pipeline at CP1 of the flange.
The system highlights the pipeline.
2. Select Move East and key in 5'6" (1676 mm).
The system reorients the piping segment.
3. Accept the form with Confirm.
The system updates the database and the graphics.
Move Pipe Run Exercises
Complete the following five exercises using the Move Pipe Run command.
Note:
See Move Pipe Run for reference information.
Exercise 1 - Distance and Direction
Move pipe run (A) down 2' (610 mm).
1. Identify the pipe run (A).
2. Select Move Down and key in 2' (610 mm).
The system reorients the piping segment.
3. Accept the form with Confirm.
Exercise 2 - Delete Pipe
Move pipe run (A) by deleting pipe.
1. Identify the pipe run (A).
2. Select Delete Pipe.
3. Identify pipe to be deleted.
The system reorients the piping segment.
4. Accept the form with Confirm.
Exercise 3 - Insert Pipe
Move pipe run (A) by adding pipe.
1. Identify the pipe run (A).
2. Select Insert Pipe.
3. Identify the location were the pipe is to be added (either elbow's CP).
4. Key in 2' (610 mm).
5. Accept the form with Confirm.
The system reorients the piping segment.
6. Accept the form with Confirm.
Exercise 4 - Concentric / Eccentric Change
Move pipe run (A) by changing reducers (concentric to eccentric).
1. Select Concentric/Eccentric Size Change.
2. Identify the reducer at the end you want fixed.
3. Select Down on the compass, flat side orientation tee = flat side reducer.
4. Accept the form with Confirm.
The system reorients the piping segment.
5. Accept the form with Confirm.
Exercise 5 - Concentric / Eccentric Change
Move pipe run (A) by changing reducers (eccentric to concentric).
1. Select Concentric/Eccentric Size Change.
2. Identify the reducer at the end you want fixed.
The system reorients the piping segment.
3. Accept the form with Confirm.
Move Pipeline End Exercise
Reconnect piping with its equipment nozzle.
Note:
See Move Pipeline End for reference information.
1. Identify pipeline end, CP1 of the flange.
2. Select Move End to Nozzle option.
3. Accept the form with Confirm.
The system updates the database and the graphics.
Replace Piping Exercise
Replace all gate valves to globe valves in a pipeline.
Note:
See Replace Piping for reference information.
1. Select Gate.
2. Select Confirm.
3. Select Globe.
4. Select Confirm.
5. Identify the pipeline.
6. Accept the form with Confirm.
The system updates the database and the graphics.
Lab
Finish placing pipeline MMA0105-XIN-2C0032-N using the commands learned in this and previous sections. Refer to figure below for detailed information.