Showing posts with label Downloads. Show all posts
Showing posts with label Downloads. Show all posts

Tuesday, April 5, 2016

Download Piping and Mechanical Handbook

Be The First To Comment
The following generic procedures related to the control of Piping and Mechanical work activities
are typical of the types of Generic Construction Project Procedures that are available:
  • Underground Piping Installation
  • Above Ground Piping Installation
  • Field Fabrication of Pipe Spools
  • Pressure Testing of Piping
  • Insulation Installation
  • Rotating Equipment
  • Column, Vessel, Tank, and Exchanger Installation
  • Boilers and Fired Heaters
Additional generic procedures related to Piping and Mechanical work operations are available on
the On-Line Reference Library.

ROLE OF THE FIELD ENGINEER IN SAFETY

The Piping or Mechanical Field Engineer is a direct contributor to the safety of the work operations at the construction site. Since all safe work operations must begin with preplanning, the Field Engineer makes a direct contribution to safety by reviewing the planned work with safety in mind. The Field Engineer is typically responsible to develop a detailed work package for work planned by the Superintendent, verify the required materials are available and obtain the required permits to perform the work. The following specific types of questions might be asked by the Field Engineer to ensure the work can be done safely:


  • How will the materials get to the work location? Can preassembly be done to avoid performing work in tight or cramped quarters?
  • Does the work require the use of hazardous materials? Are MSDS sheets available at the site for all materials that are required to be used?
  • Have all the required permits (e.g. confined space entry permits) been obtained to allow the work to be performed? Are there any special requirements that supervision or the craft need to be aware of prior to starting the work?
  • Have all special equipment tagging requirements been satisfied?
  • Are all the required materials available on the site? Have the materials been inspected for damage or flaws that might cause injury during installation?
  • Has a thorough review for potential underground obstructions such as existing utilities, energized electrical cables and process lines been performed prior to authorizing the work to proceed?
  • Is the proposed work site free of potential fire hazards? Is the housekeeping adequate?
  • Are trenches or excavations adequately sloped or shored? Is a special shoring design required due to the depth or location of the excavation or trench?
  • Have required rigging plans been prepared and approved? Have the requirements of the approved rigging plan been reviewed with the craft who will perform the work?
  • Is the scaffolding required to perform the work properly erected? Is a special scaffold design required to access the work location?

Piping and Mechanical Handbook Contents

SECTION 1CORPORATE PIPING/MECHANICAL PROCEDURES
SECTION 2SAFETY
SECTION 3DUTIES AND RESPONSIBILITIES
SECTION 4PIPING/MECHANICAL DESIGN DRAWINGS
SECTION 5PIPE SIZES AND MATERIALS
SECTION 6PIPE JOINTS AND BENDING
SECTION 7VALVES
SECTION 8STRAINERS AND TRAPS
SECTION 9FIELD PIPING GUIDELINES
SECTION 10UNDERGROUND AND EMBEDDED PIPING SYSTEMS
SECTION 11INSULATION AND HEAT TRACING
SECTION 12HANGERS AND SUPPORTS
SECTION 13CLEANING AND FLUSHING METHODS
SECTION 14LEAK TESTING
SECTION 15MECHANICAL EQUIPMENT
SECTION 16PUMPS
SECTION 17AIR COMPRESSOR SYSTEMS
SECTION 18HEAT EXCHANGERS
SECTION 19HVAC SYSTEMS
SECTION 20CHILLER SYSTEMS
SECTION 21FANS AND BLOWERS
SECTION 22CONVEYOR SYSTEMS
SECTION 23CRUSHERS AND PULVERIZERS
SECTION 24BEARINGS AND LUBRICATION
SECTION 25GLOSSARY
SECTION 26REFERENCES

Download Piping and Mechanical Handbook



Saturday, January 9, 2016

[PDF] Design Guidelines for Safety in Piping Networks

Be The First To Comment
When compared to other equipment in a hydrocarbon processing plant, the piping network is designed to the most stringent standards. Mechanical Engineering codes require a 400% safety factor in the design of these systems. The piping system is normally considered the safest part of the plant. However, even with this level of safety, reviews of catastrophic accidents show that piping system failures represent that largest percentage of equipment failures.

Since these systems are responsible for many catastrophic accidents, operations, design, and maintenance personnel should understand the potential safety concerns. The best tool that we have to prevent future accidents is to review past incidents and incorporate lessons learned into future design and operation of piping systems.

This paper will discuss various case studies that will help to illustrate the consequences of inappropriate design, operation, and maintenance of piping systems. The case studies include:

1) Check valve failures
2) Small bore piping in compressor discharge piping, 
3) Low temperature embitterment, and 
4) Hot tapping safety issues and hot tap shavings concerns.

Check Valve Failures

Check valves are important safety devices in piping. Check valves have been utilized in the process industry for many years to keep material from flowing the wrong way and causing operational or safety concerns. One common mistake is installing the check valve backwards and blocking the process flow. There is normally an arrow on the check valve designating the proper flow direction, indicating the proper installation position. There have been cases where the manufacturer showed the arrow incorrectly, which greatly hindered troubleshooting.

Continue reading in the embedded PDF....

Design Guidelines for Safety in Piping Networks


Friday, December 11, 2015

[PPT] Download Design & Construction of Piping Systems

Be The First To Comment
To know piping design basics by going through the following points:
  • Design of pressure components.
  • Pipe Span calculations.
  • Design of pipe supports & hangers.
  • Stiffness & flexibility.
  • Expansion & stresses.
  • Line expansion & flexibility.
  • Supports & anchorage of piping.

Design of pressure piping

Many decisions need be made in the design phase to achieve this successful operation, including:

- Required process fluid quantity.
- Optimum pressure-temperature.
- Piping material selection.
- Insulation selection (tracing).
- Stress & nozzle load determination.
- Pipe support standard.

The codes provide minimal assistance with any of these decisions as the codes are not design manuals.

Design of pressure components

  • Pipe Structure “static” design, not Layout design.
  • Limitations: Code, Pressure, Temperature, How long is the plant lifetime, What is the plant reliability, etc..
  • Piping designed according to B31.3 has less lifetime than B31.1 due to lower F.S.
  • Reliability of piping under B31.1 should be higher than B31.3
  • Given that the code is a product of pressure technology, one of the concerns is the pressure-temperature ratings of the components.
  • Each system be it vessel or piping has some base pressure-temperature rating. This is essentially the pressure temperature rating of the weakest member of the system. This can be translated that no minor component (valve, flange, etc) shall be the weakest link.
  • The key components of the design conditions are the design pressure and the design temperature.
  • Design pressure is defined as the most severe sustained pressure which results in the greatest component thickness and the highest component pressure rating.
  • Design temperature is defined as the sustained pipe metal temperature representing the most severe conditions of coincident pressure and temperature.
  • Thus we can try to simplify our stresses into two main categories;
  • Pressure stress is the circumferential stress (primary stress) or hoop stress, which is known to be not self limiting.
  • Temperature stress is the shear or bending stress (Secondary stress), known to be self limiting.
  • In addition VIBRATION, has to be addressed as low cycle high stress named as “thermal expansion cycles”, represented by f=1 for 7000 cycles, otherwise detailed design has to be performed to prove that the pipe will withstand high cycle, low stress loads.

Design of pressure components Wall Thickness Calculation

The code assists the designer in determining adequate pipe wall thickness for a given material and design conditions as follows:

- Calculate the pressure design thickness “t”

- Add the mechanical corrosion and erosion allowances “c” to obtain the thickness tm=t+c

- Add mill tolerance (MT) to tm, then select the next commercially available wall thickness.

- Provided t

[PPT] Design & Construction of Piping Systems


Overview of Process Plant Piping System Design by Carmagen Engineering

Be The First To Comment

Introduction

This course provides an overview of process plant piping system design. It discusses requirements contained in ASME B31.3, Process Piping, plus additional requirements and guidelines based on common industry practice. The information contained in this course is readily applicable to on-the-job applications, and prepares participants to take more extensive courses if appropriate.

What is a piping system

A piping system conveys fluid from one location to another. Within a process plant, the locations are typically one or more equipment items (e.g., pumps, pressure vessels, heat exchangers, process heaters, etc.), or individual process plants that are within the boundary of a process facility.

A piping system consists of:

  • Pipe sections
  • Fittings (e.g., elbows, reducers, branch connections, etc.)
  • Flanges, gaskets, and bolting
  • Valves
  • Pipe supports and restraints

Each individual component plus the overall system must be designed for the specified design conditions.

Scope of ASME B31.3

ASME B31.3 specifies the design, materials, fabrication, erection, inspection, and testing requirements for process plant piping systems. Process plants include petroleum refineries; chemical, pharmaceutical, textile, paper, semiconductor, and cryogenic plants; and related process plants and terminals.

ASME B31.3 applies to piping and piping components that are used for all fluid services, not just hydrocarbon services. These include the following:
  • Raw, intermediate, and finished chemicals.
  • Petroleum products.
  • Gas, steam, air, and water.
  • Fluidized solids.
  • Refrigerants.
  • Cryogenic fluids.
The scope also includes piping that interconnects pieces or stages within a packaged-equipment assembly.

The following are excluded from the scope of ASME B31.3:
  • Piping systems for internal gauge pressures at or above zero but less than 15 psi, provided that the fluid is nonflammable, nontoxic, and not damaging to human tissue, and its design temperature is from -20°F through 366°F.
  • Power boilers that are designed in accordance with the ASME Boiler and Pressure Vessel Code Section I and external boiler piping that must conform to ASME B31.1.
  • Tubes, tube headers, crossovers, and manifolds that are located inside a fired heater enclosure.
  • Pressure vessels, heat exchangers, pumps, compressors, and other fluid-handling or processing equipment. This includes both internal piping and connections for external piping.

Overview of Process Plant Piping System Design by Carmagen Engineering


Thursday, December 10, 2015

Piping Design Data Book by Hyundai

Be The First To Comment
Here's the content of the book:
  • Reference codes for piping design
  • Pressure Temperature Ratings
  • Hydrostatic Test Pressure for all material group
  • Non-destructive examination of Fabricated Pipe Welds
  • End Preparation for Welding
  • Installed Cost of Corrosion Resistant Piping
  • Relative Carrying Capacity of Pipe for Water
  • Relative Carrying Capacity of Pipe for Air, Steam and Gas
  • COADE STRESS ANALYSIS SEMINAR NOTES by COADE: Must have tutorial guide for every piping stress engineer using CAESAR II. Explains in details all the basics of Caesar II application.
  • PIPING HANDBOOK by M L Nayyar: One good book for both stress and layout engineers with huge important database on piping engineering. Refer this book for any data you require during your day to day piping works.
  • PIPE DRAFTING AND DESIGN by Rhea and Parisher: The best book for a beginner. Covers the basics in simple language. Very easy to understand.
  • PROCESS PLANT LAYOUT AND PIPING DESIGN by Hunt and Bausbacher: The best book for a piping layout engineer. Covers the basics of piping layout. Most of the preliminary layout ideas connected to any equipment evolves from this book. So read this book attentively for effective layout knowledge.

Piping Design Data Book by Hyundai


Engineering Specification of Piping Design By Toyo Engineering

Be The First To Comment

Intent

This specification covers general requirements concerning process and utility piping systems which may be included in the plant constructed by Toyo Engineering India Ltd (hereinafter referred to as PMC).

Scope

The extent of piping systems to which this specification is to be applied, shall be as indicated on the applicable piping and instrument flow diagrams (hereinafter referred to as P&I), and utility flow diagrams (hereinafter referred to as UFD). However, piping systems which are furnished as a regular part of proprietary or standardized equipment (or package unit) may be in accordance with the equipment manufacturer's standards.

Instrument piping/tubing systems from the first fitting or block valve on the piping systems shall not be covered by this specification.

The requirements for inspections and tests of piping materials, and other requirements for piping construction are not specified in this specification.

Specific Job Requirements

Specific Job Requirements which are attached to this specification cover modifications to this specification and Customer's special or local requirements as well as specific job data pertinent to this specification. Where Specific Job Requirements are in contradiction to this specification, Specific Job Requirements shall govern.

Codes and Standards

Piping systems and piping materials shall be designed and manufactured in accordance with the applicable codes and standards.

Units

Unless otherwise specified, metric, degree Celsius and kilogram units shall be applied, but nominal sizes of piping shall be in accordance with inch system (NPS). The units and numerical values given in [ ] in this specification are based on the International System of Units (SI) and are appended for reference.

Related Engineering Specifications

H-100 "Plant Layout"
H-103 "Piping Materials"
H-107 "Steam Tracing Piping"
L-101 "Thermal Insulation Design"

Piping Design Basis

Design of piping systems and materials shall be in accordance with this specification and ASME Code for "CHEMICAL PLANT AND PETROLEUM REFINERY PIPING" B31.3 & “POWER PIPING”B 31.1, unless otherwise specified in the applicable codes and standards.

Design Pressure and Temperature

(1) The design pressures and temperatures shall be determined, considering start-up, shutdown conditions and other requirements for safety as well as normal operating conditions.

(2) Design conditions for piping systems shall be summarized in "Line Schedule".

Piping Materials

(1) All piping materials shall conform to the requirements of ASTM.

(2) Materials to other national standards such as BS, DIN, JIS etc, or special materials not covered in codes and standards may be applied with approval by PMC.

(3) Detail specifications of piping materials shall be in accordance with Engineering Specification H-103 "Piping Materials".

(4) Piping material shall be properly marked for easy identification, Procedure for the same to established by LSTK contractor for marking of piping material and the shall be approved by TEIL/Owner.

Engineering Specification of Piping Design By Toyo Engineering


Wednesday, December 9, 2015

Samsung Piping Design Manual of Pump Piping

Be The First To Comment
Purpose and Application Scope

The purpose of this manual is to increase efficiency and establish standards for design by providing the basic concept necessary for piping design and the criteria for detailed design relevant to pump on the plant which is designed and/or constructed by Samsung Engineering Co., Ltd. The scope included in this manual is for the normal pumps under room temperature, and it shall not be used for special pumps.

Relevant Manuals and Standards

1.2.1 Relevant to pump layout decision criteria

(1) SEM-2002 "Plant Layout Standard (for Chemical Plant)"

1.2.2 Relevant to pump surroundings piping

(1) SEM-3039 "Piping Design Criteria"
(2) SEM-3016 "Piping Flexibility Analysis"
(3) API 610 "Centrifugal Pumps for General Refinery Service"
(4) API 686 "Recommended Practice for Machinery Installation and Installation Design"

1.2.3 Relevant to pump surroundings support

(1) SEM-3040 "Pipe Hanging No.1 (Piping Hanging Manual)"
(2) SEM-3043 "Pipe Support Design Data"

1.3 Basic Concept

1.3.1 Definition of pump

Pump is a device which give pressure to fluid passing through it and discharges the
fluid to the outside.

Samsung Piping Design Manual of Pump Piping


Monday, November 30, 2015

Mechanical Design of Process Systems-Vol 1 by A.Keith Escoe (Piping & Pressure Vessels)

Be The First To Comment
This book's purpose is to show how to apply mechanical engineering concepts to process system design. Process systems are common to a wide variety of industries including petrochemical processing, food and pharmaceutical manufacturing, power generation (including cogeneration), ship building, and even the aerospace industry. The book is based on years of proven, successful practice, and almost all of the examples described are from process systems now in operation.

While practicality is probably its key asset, this first volume contains a unique collection ofvaluable information, such as velocity head data; comparison ofthe flexibility and stiffness methods of pipe stress analyses; analysis of heat transfer through pipe supports and vessel skirts; a comprehensive method on the design of horizontal vessel saddles as well as a method to determine when wear plates are required; detailed static and dynamic methods of tower design considering wind gusts, vortex-induced vibration and seismic analysis of towers; and a comparative synopsis of the various national wind cooes.

Topics include.d in the text are considered to be those typically encountered in engineering practice. Therefore, because most mechanical systems involve single phase flow, two-phase flow is not covered. Because of its ubiquitous coverage in the literature, flange design is also excluded in this presentation. Since all of the major pressure vessel codes thoroughly discuss and illustrate the phenomenon of external pressure, this subject is only mentioned briefly.

This book is not intended to be a substitute or a replacement of any accepted code or standard. The reader is strongly encouraged to consult and be knowledgeable of any accepted standard or code that may govern. It is felt that this book is a valuable supplement to any standard or code used.

The book is slanted toward the practices of the ASME vessel and piping codes. In one area of vessel design the British Standard is favored because it nrovides excellent technical information on Zick rings. The book is written to be useful regardless of which code or standard is used.

The intent is not to be heavily prejudiced toward any standard, but to discuss the issue-engineering. If one feels that a certain standard or code should be mentioned, please keep in mind that there are others who may be using different standards and it is impossible to discuss all of them.

The reader's academic level is assumed to be a bachelor of science degree in mechanical engineering, but engineers with bachelor of science degrees in civil, chemical, electrical, or other engineering disciplines should have little difficulty with the book, provided, of course, that they have received adequate academic training or experience.

Junior or senior undergraduate engineering students should find the book a useful introduction to the application of mechanical engineering to process systems. Professors should find the book a helpful reference (and a source for potential exam problems), as well as a practical textbook for junior-, senior-, or graduate level courses in the mechanical, civil, or chemical engineering fields. The book can also be used to supplement an introductory level textbook.

The French philosopher Voltaire once said, "Common sense is not very common," and unfortunately, this is sometimes the case in engineering. Common sense is often the by-product of experience, and while both are essential to sound engineering practice, neither can be learned from books alone. It is one ofthis book's eoats to unite these three elements of "book learning," common sense, and experience to give the novice a better grasp of engineering principles and procedures, and serve as a
practical design reference for the veteran engineer.

Finally, I wish to thank Dr. John J. McKetta, professor of chemical engineering at the University of Texas at Austin, who had many helpful comments, suggestions, and words of encouragement. I also wish to thank other engineering faculty members at the University of Texas at Austin for their comments. I must exDress thanks to Larry D. Briggs for reviewing some calculations in Chapter 4; and last, but certainly not least, I wish to express gratitude to William J. Lowe and Timothy W. Calk
of Gulf Publishing Company, whose hard work and patience made this book possible.


Table of Contents:

Chapter 1
Piping Fluid Mechanics ........... 1
Basic Equations, I
Non-Newtonian Fluids, 5
Velocity Heads, 8
Pipe Flow Geometries, 22
Comoressible Flow. 25
Piping Fluid Mechanics Problem Formulation, 25
Example 1-1: Friction Pressure Drop for a Hydrocarbon Gas-Steam Mixture in a Pipe, 27
Example 1-2: Frictional Ptessure Drop for a Hot Oil System of a Process Thnk, 33
Example 1-3: Friction Pressure Drop for a Waste Heat Recovery System, 42
Example 1-4: Pressure Drop in Relief Valve Piping System, 43
Notation, 45
References, 45
Chapter 2
The Engineering Mechanics of Piping .,...47
Piping Criteria, 47
Primary and Secondary Stresses, 49

Allowable stress Range for Secondary Stresses.

Flexibility and Stiffness of Piping Systems, 52

Stiffness Method Advantages. Flexibility

Method Advantages.

Stiffness Method and Large Piping, 58
Flexibility Method of Piping Mechanics. Pipe

Loops.

PiD- e Restraints and Anchors. 68

Pipe Lug Supports. Spfing Supports. Expansion Joints. Pre-stressed Piping.

Fluid Forces Exerted on Piping Systems, 81
Extraneous Piping Loads, 83
Example 2-l: Applying the Stiffness Method to a Modular Skid-Mounted Gas Liquefaction Facility,88
Example 2-2: Applying the Flexibility Method to a Steam Turbine Exhaust Line, 95
Example 2-3: Flexibility Analysis for Hot Oil Piping,96
Example 2-42 Lug Design, 98
Example 2-5: Relief Valve Piping System, 99
Example 2-61 Wind-Induced Vibrations of Piping, 100
Notation, 101
References, 101
Chapter 3
Heat Transfer in Piping and Equipment ... 103
Jacketed Pipe versus Traced Pipe, 103
Tracing Piping Systems, 106

Traced Piping without Heat Tmnsfer Cement.

Traced Piping with Heat Transfer Cement.

Condensate Return. Jacketed Pipe. Vessel and

Equipment Traced Systems.
Heat Transfer in Residual Systems, 132

Heat Transfer through Cylindrical Shells. Residual Heat Transfer through Pipe Shoes.

Example 3-1: Steam Tracing Design, 136
Example 3-2: Hot Oil Tracing Design, 137
Example 3-3: Jacketed Pipe Design, 139
Example 3-4: Thermal Evaluation of a Process Thnk, 140
Example 3-5: Thermal Design of a Process Tank, 142

Internal Baffle Plates Film Coefficient. Film

Coefficient External to Baffles-Forced

Convection. Heat Duty of Internal Vessel

Plates. Outside Heat Transfer Jacket Plates.
Heat Duty of Jacket Plates Clamped to Bottom
Vessel Head. Total Heat Duty of Tank.

Example 3-6: Transient and Static Heat Transfer Design, 148

Static Heat Transfer Analysis. Total Heat

Removal. Water Required for Cooling.

Transient Hear Transfer Analysis.

Example 3-7: Heat Transfer through Vessel Skirts, 152
Example 3-E: Residual Heat Transfer, 154
Example 3-9: Heat Transfer through Pipe Shoe, 156
Notation, 156
References, 157

Chapter 4
The Engineering Mechanics of Pressure
Vessels ... . ..... 159
Designing for Internal Pressure, 159
Designing for External Pressure, 160
Design of Horizontal Pressure Vessels, 166

Longitudinal Bending Stresses. Location of Saddle Supports. Wear Plate Design. Zick

Stiffening Rings.

Steel Saddle Plate Design, 174
Saddle Bearing Plate Thickness, 180
Design of Self-Supported Vertical Vessels, 180
Minimum Shell Thickness Reouired for Combined Loads, 181
Support Skirt Design, 183
Anchor Bolts, 184
Base Plate Thickness Design, 186
Compression Ring and Gusset Plate Design, 189
Anchor Bolt Torque, 189
Whd Aralysis of Towers, 190
Wind Design Speeds. Wind-Induced Moments.
Wind-Induced Deflections of Towers. l ind-Induced Vibrations on Tall Towers.
Ovaling. Criteda for Vibration Analysis.
Seismic Design of Tall Towers, 209
Vertical Distribution of Shear Forces.
Tower Shell Discontinuities and Conical Sections, 1t i
Exanple 4-l: Wear Plate Requirement Analysis, 215
Example 12: Mechanical Design of Process Column. 215

Section moments of Inertial tower Section

Stress Calcularions. Skirt and Base Plate

Design- Section Centroids. Vortex-Induced

vibrarion. Equivalent Diameter Approach
versus - ANSI A58.1- 1982.

Example 4-3: Seismic Analysis of a Vertical Tower, 237
Example 44: Vibration Analysis for Tower with Large Vortex-Induced Displacements, 241

Moments of Inertia. Wind Deflections.

Example 4-5: Saddle Plate Analysis of a Horizontal Vessel, 249
Saddle Plate Buckling Analysis. Horizontal Reaction Force on Saddle.
Notation,252
References,254


Fiberglass Reinforced Piping Systems Guide

Be The First To Comment
Fiber Glass Systems’(FGS) fiberglass reinforced epoxy and vinyl ester resin piping systems possess excellent corrosion resistance and a combination of mechanical and physical properties that offer many advantages over traditional piping systems. Fiber Glass Systems is recognized worldwide as a
leading supplier of piping systems for a wide range of chemical and industrial applications.

This manual is provided as a reference resource for some of the specific properties of FGS piping systems. It is not intended to be a substitute for sound engineering practices as normally employed by professional design engineers. 

Fiber Glass Systems has an international network of distributors and trained field personnel to advise on proper installation techniques. It is recommended they be consulted for assistance when installing FGS piping systems. This not only enhances the integrity of the piping system, but also increases the efficiency and economy of the installation.

Table of Contents

Introduction

Piping System Selection

SECTION 1 — Flow Properties

Preliminary Pipe Sizing

Detailed Pipe Sizing
A. Liquid Flow
B. Loss in Pipe Fittings
C. Open Channel Flow
D. Gas Flow
SECTION 2 — Above Ground System Design Using

Supports, Anchors & Guides

Piping Support Design
A. Support Bracket Design
B. Typical Guide Design
C. Anchor Design
D. Piping Support Span Design
SECTION 3 — Temperature Effects

System Design 

Thermal Properties and Characteristics 

Fundamental Thermal Analysis Formulas
A. Thermal Expansion and Contraction
B. Anchor Restraint Load
C. Guide Spacing 
Flexibility Analysis and Design
A. Directional Change Design
B. Expansion Loop Design
C. Expansion Joint Design
D. Heat Tracing
E. Thermal Conductivity
F. Thermal Expansion in Buried Pipe
G. Pipe Torque due to Thermal Expansion 
SECTION 4 — Pipe Burial 

Pipe Flexibility

Burial Analysis
A. Soil Types
B. Soil Modulus
Trench Excavation and Preparation
A. Trench Size
B. Trench Construction
C. Maximum Burial Depth
D. Roadway Crossing
Bedding and Backfill
A. Trench Bottom
B. Backfill Materials
C. Backfill Cover
D. High Water Table 
SECTION 5 — Other Considerations 
A. Abrasive Fluids
B. Low Temperature Applications
C. Pipe Passing Through Walls or
Concrete Structures
D. Pipe Bending
E. Static Electricity
F. Steam Cleaning
G. Thrust Blocks
H. Vacuum Service
I. Valves
J. Vibration
K. Fluid (Water) Hammer
L. Ultraviolet (U.V.) Radiation and Weathering
M. Fungal, Bacterial, and Rodent Resistance
SECTION 6 — Specifications and Approvals 
A. Compliance with National Specifications
B. Approvals, Listings, and Compliance with Regulations 
APPENDICES

Appendix A Useful Formulas 

Appendix B Conversions

LIST OF TABLES
  • Table 1.0 Typical Applications 
  • Table 1.1 Flow Resistance K Values for Fittings
  • Table 1.2 Typical Liquid Properties
  • Table 1.3 Typical Gas Properties
  • Table 2.0 Minimum Support Width
  • Table 2.1 Saddle Length
  • Table 4.0 Recommended Bedding and Backfill
  • Table 4.1 Nominal Trench Widths
  • Table 6.0 ASTM 2310 Classification
  • Table 6.1 Classifying Fiberglass Flanges to ASTM D4024
  • Table 6.2 Classifying Fiberglass Pipe Using ASTM D2310 and Specifying Pipe Using ASTM D2996 and D2997


Wednesday, November 18, 2015

Selection and Limitations of Piping Components

Be The First To Comment

Selection and Limitations of Piping Components

Contents:

  • Pipes and Fittings
  • Comments on selection and Limitations of Components
  • Piping Joints
  • Fabrication, Assembly and Erection of Process Plant Piping
  • Examination , Inspection and Testing

Pipe and Fittings

Furnace lap weld ferrous pipe, furnace butt-weld ferrous pipe, spiral-weld ferrous pipe, and fusion-welded steel pipe (made to ASTM A134, A53, Type F, API 5L furnace butt welded and A211) are not permitted for hydrocarbons or other flammable fluids within process unit limits or for hazardous fluids in any location. Non-ferrous pipe made by similar manufacturing process is similarly restricted.

The use of bell-and-spigot fittings is limited to water and drainage service. Also, pipe couplings made of cast, malleable, or wrought iron are not permitted for flammable fluids within process limits or hazardous fluids in any area. In addition, they cannot be used for flammable fluids outside process unit limits at design temperatures above 300°F or design pressures above 400 psig.

Comments on Selection and Limitations of Components

There are many Code mandated restrictions for the use of fittings, bends, intersections, and valves which are not universally applicable to all process plant services, and such components are not easily codified. Some guides, however, are of value to the designer and are listed:

  • Welding fittings are usually preferred to flanged fittings, not only for economic reasons but because the potential for leakage is reduced.
  • Pipe bends are preferred to butt welding elbows for reciprocating compressor suction and discharge piping, vapour relief-valve discharge piping, and piping conveying corrosive fluids (such as acid where turbulence in a fitting may cause excessive corrosion).
  • Bends or dead end tees should be used for piping which conveys pulverized abrasive solids suspended in gas in the dilute phase. Dead end tees (so arranged that the flow will impinge against the dead end) have a longer life than bends in abrasive service and should be used if the system can be designed to accommodate the resulting increase in pressure drop.
  • Bends should be used for dense phase flow of pulverized abrasive solids and for all piping which handles either pulverized or granular solids suspended in liquids or granular solids suspended in gases.
  • If the flow is through a branch into a header (or run pipe) in a piping system which transports pulverized abrasive solids suspended in gas in the dilute phase, a dead end cross (so arranged that the flow will impinge against the dead end) should be used.
  • In services with very high corrosion rates, butt welding fittings with the same inside diameter (ID) as the attached pipe (if not the same, consider taper boring the component with the smaller ID) are preferred to threaded and socket welding fittings.
  • Threaded cast iron fittings should not be used in pressurized process and utility piping.
  • Threaded plugs are preferred to pipe caps for threaded end closures to reduce dead end corrosion problems.
  • In most process plants, internal corrosion is a greater problem than external corrosion. Consequently, it is common practice that all 3/4 in and larger steel and cast iron (and all 2 1/2 in and larger brass) gate, globe, and angle valves (located above grade) be of the outside screw and yoke type.
Read more in embedded PDF:


Friday, October 16, 2015

[XLS] Download Process, Piping, Instrumentation, Mechanical, Drilling and Civil Design Spreadsheets

Be The First To Comment
Here a big list of spreadsheets available for download from Piping, Process, Instrumentation, Mechanical, Drilling and Civil.


Beam and Pipe Spreadsheets:

  1. CALCULO SOPORTES.xls
  2. DIÁMETROS DE TUBERIA.xlsx
  3. header_&_Piping_sizing.xls
  4. piping_design_info.xls
  5. PIPINGS_AND_FITTINGS.xls
  6. POLIN TIPO-A.xls
  7. POLIN TIPO-B.xls
  8. Prontuario del Acero.xls
  9. QCF522_FIRED_HEATER_-_INSTALLATION_OF_STACK,_PIPING_AND_OUTLET_MANIFOLD.xls
  10. Steel_Pipe_Dimens.xls
  11. stress_tables.xls
  12. Tablas Varias.xls
  13. Useful_Piping_&_Structural_Data.xls


Civil Engineering Spreadsheets

  1. Bar Schedule 8666.xlt
  2. Daniel-Conventional Slabs.xls
  3. Daniel-Pile Caps.xls
  4. Daniel-Tank Footing.xls
  5. Daniel-Wind-ASCE7-05.xls
  6. Daniel-Wind-IR16-7.xls
  7. Steel Beam.xls
  8. Tank Size Calculator.xls
  9. Wind Design.xls


Thursday, October 1, 2015

Download PDS Equipment Modelling Training Guide

Be The First To Comment

Download PDS Equipment Modelling Training Guide

Table of Contents

Preface
  • Terminology and Conventions
  • Course Overview
1.1 Rules for Orientation Tee
1.2 Suggestions for Screen Management
1.3 Setting Up
1.4 Orienting the Placement Tee
1.5 Moving the Placement Tee

2. Basic Equipment Manipulation Exercises
2.1 Setting Up
2.2 Creating Equipment Using Primitives
2.3 Identifying and Manipulating Equipment

3.1 Setting Up
3.2 Creating Components Using Primitives
3.3 Manipulating Components

4. Parametrics Exercises
4.1 Setting Up
4.2 Creating Equipment Using Parametrics
4.3 Creating Components Using Parametrics
4.4 Manipulating Parametrics

5. Nozzle Manipulation Exercise
5.1 Setting Up
5.2 Placing Nozzles
5.3 Parametrics
5.4 Manipulating Nozzles

6.1 Setting Up
6.2 Using the Mirror Copy Command
6.3 Using the Rotate Command
6.4 Using User-Projected Shapes
6.5 Using Fence Manipu fations
6.6 Using Review/Revise

7. Lab Exercises
7 .1 Lab
7.1.1. Horizontal Vessel 38V-101
7.1.2 Reboiler 38E-102
7.1.3 Fractionating Tower 38TW-102
7 .1.4 Place the Nozzle

7 .2 Lab 2
7.2.1 Horizontal Pumps 38P-101A and 38P-101 B
7.2.2 Heat Exchangers
7 .2.3 Fractionating Tower Detail 38TW-102

Course Overview

Prerequisites
• Familiarity with the use of Intergraph hardware.
• Basic knowledge of MicroStation 3-D.
• Drafting experience.

Course Description

This course addresses the creation of a 3-0 equipment model usin g the PDS equipment modeling software. Upon completion of this course you should be able to:

  • Create an equipment model using basic shapes (primitives).
  • Create an equipment model using parametrics.
  • Manipulate equipment model's components.
  • Manipulate equipment models .
Course Organization

This course is organized in a series of lectures that are supported by a laboratory exercise at the end of each lecture. Commands are explained in order of importance rather than as they appear in their group. For descriptions of commands in sequential order ref er to the PDS Equipme nt Modeling Reference Guide (DEA5017).


Monday, September 28, 2015

Download PDS Piping Design Training Workbook

Be The First To Comment

Download PDS Piping Design Training Workbook

Table of Contents

1. Getting Started

1.1 Setting up Workstation Environment
1.2 Reference Model Exercise
1.3 PDS Rules for Better Living

2. Component Placement

2.1 Place Component Exercise
2.2 Connect to Design Exercises
2.3 Point in Space Exercises
2.4 Place Pipe Exercise
2.5 Labs
1. Place components
2. Identification of components, segments, and equipment
3. Active Segment Data

3.1 Active Segment Data Exercise
3.2 Updating the Active Segment Data Exercise

4. Basic Sketching

4.1 Review Nozzle Exercise
4.2 Sketch Exercise
4.3 Slope On/Off Exercise
4 .4 Alive Slope Exercise
4.5 Move Piping Segment Vertex
4.6 Delete Piping Segment Vertex Exercise
4. 7 Insert Piping Segment Vertex Exercise
4.8 Attribute Break Exercise
4.9 Connect Segments Exercise
4. 10 Revise Segment Data Exercise
4.11 Revise Attribute Exercise
4.12 Auto Placement Exercise
4.13 Delete Piping Exercise
4.14 Delete Component Exercise
4.15 Labs
1. Fitting to Fitting and Sketch
2. Sketch and Construct Point
3. Sketching between Nozzles
4. Sketching from Lab 3.5.1 
5. Advanced Sketching

5.1 Distance and Direction Exercise
5.2 Extend or Shorten Pipe Run Exercise
5.3 Create Bypass Exercise
5.4 Intersect to Branch Exercise
5.5 Intersect Sloped Pipe Run Exercise
5.6 Intersect by Angles Exercise
5. 7 Intersect Plane Exercise
5.8 Skewed Intersection Exercise
5.9 Branch on Pipe Run Exercise
5.10 Create Branch through Sketch Exercises
5.11 Labs
1. Sketching pipeline DOW0102-XIN-2C0032-N
2. Sketching pipeline DOW0101-XIN-2C0032-N
3. Sketching pipeline DOW0103-XIN-2C0032-N
6. Specialty Placement

6. 1 Piping Assembly Exercise
6.2 Piping Specialty Exercise
6.3 Instrument Exercise
6.4 Commodity Options Exercise
6.5 Commodity Override Exercise
6.6 Place Logical Support Exercise
6.7 Place Physical Pipe Support Exercise
6.8 Labs
1. Adding Valves to DOW0103-41N-2C0032-N
2. Adding flanges and tees using bend to tee type to DOW0103-41N-2C0032-N
3. Adding Valves to DOW0103-41N-2C0032-N
4. Sketching pipeline MMA0105-XIN-2C0032-N
7. Component Revision

7.1 Rotate Component Exercise
7.2 Tap Component Exercise
7.3 Revise Tap Exercises
7 A Reconstruct Component Exercises
7.5 Add Chain Wheel Exercise
7.6 Add to Valve Exercises
7. 7 Revise Pipe Exercise
7.8 Move Piping Assembly Exercises
7.9 Delete Piping Assembly Exercises
7.10 Move Pipe Support Exercise
7.11 Copy Pipe Support Exercise
7.12 Labs
1. Placing valve assembly to DOW0102-61N-2C0032-N
2. Continue MMA010561N-2C0032-N
8. Model Revision
8.1 Copy Piping Exercise
8.2 Rotate Piping Exercise
8.3 Copy and Rotate Piping Exercise
8.4 Mirror Piping Exercise
8.5 Copy and Mirror Piping Exercise
8.6 Move Piping Exercise
8.7 Move Pipe Run Exercises
8.8 Move Pipeline End Exercise
8.9 Replace Piping Exercise
8.10 Lab
1. Continuation of MMA0105-XIN-2C0032-N
9. Diagnostics

9.1 Labs
1. Highlight Piping on Segment
2. Com pare Segments
3. Verify Data Integrity of Model
4. Venfy Nozzle at Pipeline End
5. Review Attribute Linkage
6. Measure Distance
7. Review Commodity Data and Tables
8. Review COG and Weights
10. Attribute Data

10. 1 Review Attributes Exercises
10.2 Load Weld Numbers Exercise
10.3 Revise Weld Type Exercises
10.4 Component Group Exercises
10.5 Approve Piping Exercise
10.6 Lab
1. Sketching/Place MMA0107-XIN-2C0032-N
11. Miscellaneous PDS Commands

11. 1 Review Category Exercise
11.2 Saved Model View Exercise
11.3 Temporary Symbology Exercises
11.4 Window to Named Item Exercises
11.5 Lab
1. Temporary Symbology
2.Creating a Saved View
12. Design Checker

12.1 Design Checker Exercise
12.2 Design Checker Review Exercise
12.3 Labs
1. Run Design Checker
2. Printing design checker .de file
3. Reviewing Design Checker graphically
13. Isometric Extraction

13. 1 Isometric Extraction
13. 1.1 Review ISO Drawings Exercise
13.2 Labs
1. Generating Isometrics
2. Isometric Drawing Limits

Tuesday, September 22, 2015

Solidworks Piping and Training Manual

Be The First To Comment

Solidworks Piping and Training Manual

Piping Basics

Introduction
  • Activating SolidWorks Piping 
  • Specifying Piping Options 
Required Features of Piping Parts 
  • Pipes 
  • Route Points 
  • Connection Points
  • Elbows 
  • Flanges 
  • Reducers 
  • Concentric Reducers 
  • Eccentric Reducers 
  • Other Fittings and Parts
  • Intersections
Creating a Piping Sub-Assembly 
  • Creating a Route 
Editing a Piping Sub-Assembly
  • Adding Fittings 
  • Manually Adding a Fitting 
  • Alternative Method for Adding Fittings 
Custom Pipe Configurations
Custom Elbow Fittings 
  • Review of Basics 
Part Naming of Sub- Assemblies
Tees, Flanges, and Standard Elbows
  • Introduction
  • Naming the Route Assembly 
  • Adding More Pipe
  • Adding a Tee 
  • Butting Standard Parts Together
  • Adding a Butterfly Valve and Flanges 
  • Adding a Victaulic (or flex) Coupling
  • Groove Cut Pipe Ends
  • Adding a Concentric Reducer
  • Adding Other Mated Flanges to the Route Assembly
Non-standard Elbows
  • Introduction
  • Adding a Custom Elbow
  • Looking at the Custom Elbow 
  • Breaking Up the Route
  • Changing an Elbow
  • Adding a Standard 45 Degree Elbow
  • Adding a Reducing Elbow
  • Adding an Eccentric Reducer
  • Butting Elbows Together
Non-Standard Pipe Connections
  • Introduction
  • Pipe to Pipe Penetration 
  • Creating an Offset Pipe Penetration (or Stub-in) 
  • Adding a Coupling 
  • Adding a Mounting Bracket
  • Creating a Custom Mount 
  • Forming Sub-Assemblies
  • Adding Parts After Sub-Assemblies are Formed
  • Adding Another Route Assembly
Routing Tubing
  • Introduction
Auto Mate
  • Introduction

SolidWorks Piping product brings the timesaving performance of SolidWorks to the task of designing piping systems. Built-in capability includes the ability to assemble piping networks built of standard content (from SolidWorks, fitting vendors or other suppliers) along with customer-developed content.

SolidWorks Piping was developed to be able to design systems requiring a wide range of piping technologies including butt-welded, socket connected, flanged, and thread-connected systems. In all cases, the fundamental capabilities of SolidWorks are maintained — including building on the 3D sketcher and the power of configurations to drive variations on the necessary fittings and parts. In fact, SolidWorks Piping only adds two more toolbar icons to the standard assortment provided by SolidWorks.

This guide provides detailed examples for developing pipe routes constructed of welded pipe and tubing components. These examples are included on the CD that accompanies this book. A piping sub-assembly is always a top-level assembly component.

When you insert certain components into an assembly, a piping subassembly is created for you automatically. Unlike other types of subassemblies, you do not create a piping assembly in its own window, and then insert it as a component in the higher-level assembly.

You model the path of the pipe by creating a 3D sketch of the pipe centerline. The software uses the centerline definition to generate the pipe and elbow components for the route.

The software makes extensive use of design tables to create and modify the configurations of piping components. The configurations are distinguished by different dimensions and properties.

A pipe part contains a configuration for each type and size of raw stock. As you create and edit the route, a new configuration is generated automatically for each unique cut length of the selected stock. The configurations are saved in a new pipe part; the original pipe part in the library folder is not changed.

Where there are bends in the path, elbows are added automatically. You specify a default elbow fitting to be used at each bend in the route. You can add various types of fittings to the route, such as flanges, tees, reducers, and so forth.

Sunday, September 20, 2015

Samsung Piping Design Manual of Tankyard Piping

Be The First To Comment

Samsung Piping Design Manual of Tankyard Piping

Table of Contents

1. General Page
1.1 Purpose
1.2 Scope
1.3 Reference

2. Type of Tank
2.1 Classification by Shape of Tank
2.2 Classification by Installing Method of Tank

3. Arrangement Plan
3.1 Tank
3.2 Dike
3.3 Pipe Rack and Sleeper
3.4 Pump Station
3.5 Stair Way
3.6 Drainage

4. Tankyard Piping
4.1 Process and Utility Piping
4.2 Fire Extinguishing Piping

5. Tank Nozzle Orientation
5.1 Cylindrical Tank
5.2 Spherical Tank
5.3 Horizontal Tank

6. Revision History

Purpose
This Manual has its purpose on increasing efficiency for piping design of tankyard in a plant designed by SECL and providing uniformity.


Samsung Vessel & Drum Piping Design Standard

Be The First To Comment

Samsung Vessel & Drum Piping Design Standard

Table of Contents

Page
1. General
1.1 Purpose
1.2 Scope
1.3 Reference
1.4 Terms and Definition

2. DRUM & VESSEL Summary
2.1 DRUM Type
2.2 DRUM & VESSEL Type
2.3 DRUM & VESSEL Arrangement
2.4 DRUM & VESSEL Installation
2.5 NOZZLE ORIENTATION & PLATFORM Arrangement
2.6 VESSEL Piping Design Standard

3. REACTOR
3.1 REACTOR Arrangement
3.2 REACTOR NOZZLE ORIENTATION & PLATFORM
3.3 REACTOR Piping Design Standard

4. VESSEL ORIENTATION
4.1 Orientation
4.2 PIPE SUPPORTS AND GUIDES
4.3 SKIRTS AND ACCESS OPENINGS
4.4 NAMEPLATES
4.5 LADDERS AND PLATFORMS
4.6 PLATFORM PENETRATING SLEEVES
4.7 DAVITS

5. VERTICAL VESSEL ORIENTATION
5.1 VERTICAL ORIENTATION REQUIREMENTS
5.2 ORIENTATION INFORMATION DRAWING Drafting
5.3 VERTICAL VESSEL ORIENTATION
5.4 PIPE SUPPORT AND GUIDE

6. HORIZONTAL VESSEL ORIENTATION
6.1 ORIENTATION REQUIREMENTS
6.2 ORIENTATION INFORMATION DRAWING
6.3 HORIZONTAL VESSEL ORIENTATION Standard
6.4 LADDER & PLATFORM

7. VERTICAL VESSEL ORIENTATION Design Standard
7.1 General
7.2 LADDER AND PLATFORMS
7.3 MANHOLES
7.4 PROCESS NOZZLES
7.5 MISCELLANEOUS NOZZLES
7.6 PIPE SUPPORTS AND GUIDES
7.7 VESSEL DAVITS
7.8 MISCELLANEOUS ITEMS

8. HORIZONTAL VESSEL Design Standard
8.1 General
8.2 LADDERS AND PLATFORMS
8.3 MANHOLES
8.4 NOZZLES
8.5 MISCELLANEOUS ITEMS

9. Revision History

Appendix

Ⅰ : Vessel Orientation - Elevation
Ⅱ : Platform with Manhole In Traffic Pattern
Ⅲ : Step Off Platform
Ⅳ : First or Grade Plan Platform
Ⅴ : Platform with Manhole in Traffic Pattern
Ⅵ : Top Head Platform
Ⅶ : Horizontal Vessel Layout - General Arrangement
(Elevation within Structure)
Ⅷ : Horizontal Vessel Layout - General Arrangement (Plan)
Ⅸ : Horizontal Vessel Layout - General Arrangement (End Typical Elevation)
Ⅹ : Horizontal Vessel Layout - General Arrangement (Elevation at Grade)
ⅩⅠ : Access Requirements for Vessels
ⅩⅡ : Minimum Ladder Clearances
ⅩⅢ : Layout - Minimum Platform Width Requirements for Manholes
ⅩⅣ : Platform Layout Guide
ⅩⅤ : Platform - Nozzle Clearances and Projections
ⅩⅥ : Platform Opening - Banding
ⅩⅦ : Davits
ⅩⅧ : Skirt Height and Opening
ⅩⅨ : Simplified Method of Drawing 2:1 Semi - Elliptical Head

Purpose
This Manual is to enhance efficiency and systemize Drum, Vessel, and Piping Design around general Reactor in Plan to be designed by SECL.


Samsung Piping Design Standard around Fired Heater

Be The First To Comment

Samsung Piping Design Standard around Fired Heater

Table of Contents

Page
1. General
1.1 Purpose
1.2 Scope
1.3 Reference
1.4 Terms and Definition

2. Heater General
2.1 Heater Type
2.2 Heater Major Components
3. Heater Layout

3.1 General 
3.2 Arrangement Height
3.3 Maintenance Area
3.4 Operation Space
3.5 Structure & Platform
3.6 Steam Drum
3.7 Crossover & Jump-over

4. Piping Layout
4.1 Process Piping
4.2 Burner Piping
4.3 Snuffing Piping
4.4 Soot Blower Piping

5. Notice in Drafting
5.1 Stress Analysis
5.2 Information to be Handled

6. Revision History 

APPENDIX
Ⅰ. Process Pipings
Ⅱ. Burner Pipings
Ⅲ. Stiffener Ring Size

Purpose
This Manual aims to enhance the efficiency and standardize the Piping Design around Heater (or Direct Fired Heater, Furnace, Reformer, etc, Heater) of Chemistry, Oil, and Oil Refinery to design by SECL.


Samsung Piping Design Manual of Underground Piping

Be The First To Comment

Samsung Piping Design Manual of Underground Piping

Table of Contents

1. GENERAL
1.1 Purpose
1.2 Scope
1.3 Kind of UNDERGROUND PIPING
1.4 Reference

2. Summary of Classification of UNDERGROUND PIPING
2.1 SEWER PIPING
2.2 TRENCH PIPING
2.3 WATER PIPING
2.4 UNDERGROUND PIPING by Other PROCESS REQUIREMENT

3. General Guideline of Design
3.1 Priority Item of Installment Plan
3.2 Regulation of TRENCH LINE
3.3 Regulation of FLANGE CONNECTION
3.4 Minimum Laying Depth of UNDERGROUND Piping
3.5 Pipe Laying SPACE
3.6 Marking System of PIPE ELEVATION
3.7 Connection with ABOVEGROUND Pipe
3.8 UNDERGROUND Pipe Protection
3.9 Prior-Consideration of Thermal Expansion

4. COOLING WATER PIPING
4.1 General Design Guideline
4.2 COOLING WATER PIPING Material

5. SEWER PIPING
5.1 Pipe Material in Use
5.2 OILY SEWER & CHEMICAL SEWER Design Guideline
5.3 Marking System in Piping Drawing
5.4 FLOW SHEET Preparation of SEWER SYSTEM
5.5 NON-OILY SEWER SYSTEM

6. TRENCH Pipe
6.1 Application Scope
6.2 General Form

7. UNDERGROUND PIPING Drawing Manual
7.1 General
7.2 Drawing Manual Standard
7.3 Drawing Marking System

8. Revision History 

Appendix
Ⅰ : UNDERGROUND PIPE Thickness Calculation Standard
Ⅱ : UNDERGROUND PIPE Thickness Certification Bill by using Achievement Results
Ⅲ : SEWER SIZE Decision Example & HYDRAULIC TABLE
Ⅳ : Steel Pipe SIZE & Flow and Speed by Slope
Ⅴ : MITER BEND & FABRICATION TEE DIMENSION
Ⅵ : FLOW SHEET Preparation Example
Ⅶ : DETAILS OF PIT COVER


Samsung Compressor and Turbine Piping Design Standard

Be The First To Comment

Samsung Compressor and Turbine Piping Design Standard

Table of Contents

Page
1. General
1.1 Purpose
1.2 Scope
1.3 Reference

2. COMPRESSOR General
2.1 Compressor Types and Characteristics
2.2 Compressor Comparison

3. COMPRESSOR/TURBINE LAYOUT
3.1 Layout General
3.2 Compressor House Layout
3.3 Installation Height
3.4 Operation & Maintenance

4. Piping LAYOUT
4.1 Compressor Connecting Pipe
4.2 Turbine Connecting Pipe
4.3 Oil System Connecting Pipe
4.4 Strainer Installation
4.5 Expansion Joint Installation

5. NOZZLE Load Calculation Procedure & Consideration
5.1 Standard
5.2 Calculation & Review Procedure
5.3 Consideration

6. PIPING SUPPORT
6.1 Compressor/Turbine Support General
6.2 Support Consideration by Compressor
6.3 Consideration by Support Type
6.4 Structure Strength by Support

7. Work Activity by Design Phase

8. Revision History

APPENDIX
Ⅰ. Compressor Pipe Fixed Point Selection Method
Ⅱ. Compressor Pipe Construction Method(SAMPLE)
Ⅲ. Reference Plot Plan (MOP, GSP-5, PEMEX-Tula, IOCL)

Purpose
This Manual aims to reinforce and standardize the Piping Layout (Incl Supports) for Compressor
/Turbine systems for oil refinery and Chemical Plants designed by SECL.


Samsung Piping Design Manual - Rack Piping

Be The First To Comment

Samsung Piping Design Manual - Rack Piping

Contents

1. GENERAL

1.1 Purpose
1.2 Application Scope
1.3 Relevant Manuals

2. PIPING DESIGN CRITERIA

2.1 Rack piping design criteria
2.2 General piping design criteria

3. RACK ARRANGEMENT

3.1 Items to be considered
3.2 Typical Layout

4. RACK HEIGHT

5. PIPING ARRANGEMENT AND DECISION ON THE RACK WIDTH

5.1 Piping Arrangement
5.2 Rack Width

6. LOADING DATA

6.1 Type of Load
6.2 Calculation Method
6.3 Layout Aids for Piperack
6.4 Weight Table for Thermal Insulation (for reference)

7. EXPANSION LOOPS

8. RACK STRUCTURE (FOR REFERENCE)

9. HISTORY OF THIS MANUAL

Appendix Ⅰ Sample of pipe rack loading data information drawing

Appendix Ⅱ Sample of calculation table for maximum bending stress, anchor force and friction
force


 

© 2011 PIPING GUIDE - Designed by Ankit | ToS | Privacy Policy | Sitemap

About Us | Contact Us | Write For Us